  "as_of": "2026-06-22",
  "cited_project_id": "C01-1012",
  "hash_verified": true,
  "raw_file_sha256": "941c85f6edf77026e68e9845fd119fdd5027de8e7ed5c942c65888d0b4cee8a1",
  "row_values": {
    "Actual In-Service Date": null,
    "Backfeed Date": null,
    "CSA/USCA Report": null,
    "CSA/USCA Report Status": "Not Started",
    "Capacity or Energy": "CAPACITY_RESOURCE",
    "Commercial Name": null,
    "Commercial Operation Milestone": null,
    "County": "Middlesex",
    "Cycle": "C01",
    "Developer": "Heritage Power Marketing, LLC",
    "EPA/GIA/WMPA Report": null,
    "EPA/GIA/WMPA Report Status": "Not Started",
    "Final SIS Report": null,
    "Final SIS Report Status": "Not Required",
    "Fuel": "Storage",
    "LTF MW": null,
    "Last Updated": "5/30/2025",
    "MFO": "211.3",
    "MW Capacity": "0.0",
    "MW Energy": "0.0",
    "MW In Service": "0.0",
    "Name": null,
    "Phase 1 SIS Report": null,
    "Phase 1 SIS Report Status": "Not Required",
    "Phase 2 SIS Report": null,
    "Phase 2 SIS Report Status": "Not Required",
    "Phase 3 SIS Report": null,
    "Phase 3 SIS Report Status": "Not Required",
    "Project ID": "C01-1012",
    "Project Type": "Generation Interconnection",
    "Requested In-Service Date": "11/24/2028",
    "Rights (MW)": null,
    "Stage": "Application Submission",
    "State": "NJ",
    "Status": "Withdrawn",
    "Submitted Date": "5/30/2025",
    "TSR End Date": null,
    "TSR ID": null,
    "TSR Start Date": null,
    "Test Energy Date": null,
    "Transmission Owner": "JCPL",
    "Transmission Type": null,
    "Withdrawn Date": "7/10/2025",
    "Withdrawn Remarks": "CIW"
  },
  "sheet": "Data",
  "source_file": "pjm-cycle_2026-06-22_sample.xlsx",
  "source_id": "energy.pjm.cycle",
  "source_row": 2,
  "source_url": "https://www.pjm.com/planning/m/cycle-service-request-status"
}